₹3,448.00

per m²

Materials

Resource Coeff. Unit Rate Amount
Clear float glass 6 mm thick (IS: 14900) both sides 2 sqm 450 900
Perforated aluminium spacer 12 mm (IS: 737) 4 Rmt 60 240
EPDM gasket (IS: 13646) 4 Rmt 25 100
Desiccant (Molecular sieve) 0.05 kg 800 40
Primary sealant (Polyisobutylene) 0.1 kg 600 60
Secondary sealant (Silicone) 0.15 kg 700 105

Labour

Resource Coeff. Unit Rate Amount
Mason 1st class 0.4 day 476 190.4
Beldar 0.8 day 320.83 256.66
Wireman 0.2 day 374.5 74.9
Carpenter 2nd class 0.2 day 374.5 74.9

Plant

No plant component for this item.

Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.

Need more than one rate?

Build a full BOQ with every item priced, or open this item in EstimateNext.

Looking for something else? Search all items →

About this rate

How is the rate for Providing and fixing double glazed hermetically sealed glazing in aluminium windows, ven… calculated?
It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
What is the unit of measurement?
The rate of ₹3,448.00 is per m². Multiply by your quantity to estimate the line total.
Chat on WhatsApp