Earth work in filling in foundation trenches or plinth with good earth, in layers not ex…
Indicative unit rate and the full material, labour and plant build-up — per % cum.
Earth work in filling in foundation trenches or plinth with good earth, in layers not ex…
per % cum
Indicative unit rate
₹49,179.00
per % cum
Materials
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Good earth (carried from borrow area) | 100 | cum | 350 | 19,809.56 |
| Truck 10 T charges (for earth cartage, avg lead 1 km) | 30 | hour | 474.3 | 8,053.43 |
| Fuel charges (for earth cartage) | 30 | hour | 497.1 | 8,440.57 |
Labour
| Resource | Coeff. | Unit | Rate | Amount |
|---|---|---|---|---|
| Mason 1st class | 2 | day | 816 | 923.69 |
| Beldar | 10 | day | 736 | 4,165.67 |
| Mazdoor (for watering and ramming) | 8 | day | 736 | 3,332.53 |
Plant
No plant component for this item.
Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.
Need more than one rate?
Build a full BOQ with every item priced, or open this item in EstimateNext.
Looking for something else? Search all items →
About this rate
- How is the rate for Earth work in filling in foundation trenches or plinth with good earth, in layers not ex… calculated?
- It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
- What is the unit of measurement?
- The rate of ₹49,179.00 is per % cum. Multiply by your quantity to estimate the line total.