Skip to content
ConstructionTools by SoftNext Solutions

Earth work in filling in foundation trenches or plinth with good earth, in layers not ex…

Indicative unit rate and the full material, labour and plant build-up — per % cum.

Earth work in filling in foundation trenches or plinth with good earth, in layers not ex…

per % cum

Indicative unit rate

₹49,179.00

per % cum

Materials

Resource Coeff. Unit Rate Amount
Good earth (carried from borrow area) 100 cum 350 19,809.56
Truck 10 T charges (for earth cartage, avg lead 1 km) 30 hour 474.3 8,053.43
Fuel charges (for earth cartage) 30 hour 497.1 8,440.57

Labour

Resource Coeff. Unit Rate Amount
Mason 1st class 2 day 816 923.69
Beldar 10 day 736 4,165.67
Mazdoor (for watering and ramming) 8 day 736 3,332.53

Plant

No plant component for this item.

Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.

Need more than one rate?

Build a full BOQ with every item priced, or open this item in EstimateNext.

Looking for something else? Search all items →

About this rate

How is the rate for Earth work in filling in foundation trenches or plinth with good earth, in layers not ex… calculated?
It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
What is the unit of measurement?
The rate of ₹49,179.00 is per % cum. Multiply by your quantity to estimate the line total.
Chat on WhatsApp