Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust fr…

Indicative unit rate and the full material, labour and plant build-up — per m.

Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust fr…

per m

Indicative unit rate

₹8.25

per m

Materials

Resource Coeff. Unit Rate Amount
Chemical Rust Remover 1 litre 290 4.42

Labour

Resource Coeff. Unit Rate Amount
Painter 0.16 day 816 2.01
Coolie 0.16 day 736 1.82

Plant

No plant component for this item.

Where this comes from: reference rates from real, live projects. Indicative for early-stage estimating — verify before tender.

Need more than one rate?

Build a full BOQ with every item priced, or open this item in EstimateNext.

Looking for something else? Search all items →

About this rate

How is the rate for Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust fr… calculated?
It is built up from the material, labour and plant resources shown, with reference rates from real, live projects. Figures are indicative — verify against current market rates before tender.
What is the unit of measurement?
The rate of ₹8.25 is per m. Multiply by your quantity to estimate the line total.